Floors – Pour 2
September 29, 2008 by Annie Tennis · Leave a Comment
First, here’s a quick picture of the concrete poured on Saturday.
The crew was onsite bright and early to start today’s pour. With rain forecasted for the evening/night the crew only poured until noon. But they still managed to finish about 12,000 square feet.

Before the Floors…
September 22, 2008 by Annie Tennis · Leave a Comment
Before the concrete floors can be poured, the concrete crew needed to prep the interior of the building. During the second half of last week the crew started this prep work.
Step 1: move dirt into the interior of the building.
Step 2: use dirt from step 1 to fill in any area not level with the stone.
Meanwhile, the plumbers started work in the front office area.
Step 3: use a special truck to shoot stone into the interior of the building.
Step 4: level the area.
Step 5: repeat.
Reinforcement
September 10, 2008 by Annie Tennis · 1 Comment
The Data Cave facility is going to be one strong building.
One of the many things we have done (or plan to do) is to dig deep footers and use a massive amount of rebar.
Below is a picture of where two interior footers meet. Notice the amount of rebar in this small space.
And here’s the finished product.
A Short Week
September 9, 2008 by Annie Tennis · Leave a Comment
Due to the holiday and some inclement weather, the crews only worked just over three full days.
Tuesday morning began with a majority of the interior footers constructed.
A few members of the block crew arrived on Tuesday to layout block.
In the meantime, the concrete crew continued on with the footers. Pictured below is the interior east wall.
Here is another picture of the interior east wall. This shot was taken during the concrete pour. The individual in the foreground is placing the rebar for this footer.
Later in the week, the block crew started the first two courses of brick.
Before the block crew got too far along, we ran additional conduit inside the building. This conduit will allow us to connect the two separate fiber connections together.
Unfortunately rain kept the crews from working most of the day Friday. Here’s a picture of the entire site from late Thursday, as you can see, quite a bit was completed.
Data Suite: Outlined
September 3, 2008 by Annie Tennis · 2 Comments
I visit the construction site at least twice a day. Now that the footers are underway, you can really get a feel for the layout of the building. It’s one thing to see an 84,000 square foot building on paper and another to see the orange paint on the ground marking the corners.
Since the crew has completed the majority of the interior footers, the size of each individual data suite has come to life. The size of the footers gives a false sense of the actual room size so I’ve added a blue outline to better show each data suite. Each of these 28 data suites is 1323 square feet and will accommodate up to 80 racks.