Electrical Switch Gear
April 29, 2009 by Annie Tennis · Leave a Comment
Last week, we moved the electrical switch gear for the first quadrant of the building into place.
The Week in Pictures
April 24, 2009 by Annie Tennis · 1 Comment
Over the past week, quite a bit of work has been done.
The Roof
April 22, 2009 by Annie Tennis · Leave a Comment
Just a little bit ago, I ventured up to the roof of Data Cave.
The Office Area and Steel
April 16, 2009 by Annie Tennis · Leave a Comment
In the first floor office area, work continues on the electrical wiring, network cabling, and the plumbing.
Steel, Stairs, and Office Updates
April 9, 2009 by Annie Tennis · Leave a Comment
There’s been quite a bit of activity over at the site this week.
The Last Block
April 3, 2009 by Annie Tennis · Leave a Comment
This afternoon, Caleb laid the last of 93,000 blocks (yes, he isn’t a very good block layer).

Block and the Office Area
April 2, 2009 by Annie Tennis · Leave a Comment
Block work continues on the east and west interior customer hallway walls.