Fire Suppression

September 25, 2009 by Annie · Leave a Comment 

Fire suppression systems have been installed in a handful of data suites.

Read more

The Fence

September 18, 2009 by Annie · 1 Comment 

The fence around the perimeter of Data Cave is now complete.

Read more

Additional UPS Capacity

September 15, 2009 by Annie · Leave a Comment 

A few weeks ago, we ordered additional flywheels for our UPS systems.

Read more

Blogging Hiatus

September 15, 2009 by Annie · Leave a Comment 

I apologize for the lack of blog post this past month.  Although, I haven’t been blogging about the progress being made at Data Cave, our crew has been hard at work.  I plan to elaborate on most of these items in the next week or two but here are a few things we’ve been working on:

  • increasing the capacity of the UPS systems,
  • data center cooling (processed water, chillers,etc.),
  • completion of the fence around the perimeter,
  • installation of additional fire suppression systems for individual data suites,
  • additional network configuration,
  • testing of monitoring systems, and
  • installation and configuration of security systems.

Additionally, we’ve been finishing up the front office area and we’ve also moved into the new facility.