Block, Paint, and Sprinklers
March 12, 2009 by Annie Tennis · 1 Comment
Progress on the second floor block is coming along nicely.
The walls for the customer hallway are complete.

Seven courses of block have been laid on all of the east/west walls on the west side of the building.

Work has begun on the east side of the building.

In Shipping/Receiving, the steel has been painted.

The walls have been painted with block fill (aka primer) and the steel has been painted.

The sprinkler system for the front office has been installed. The sprinkler system can also be seen in the previous picture.