AC, Lights, and the Parking Lot
There has been lots of activity at Data Cave in the past few weeks. In this blog, I’ll touch on AC, lights, and the parking lot.

There has been lots of activity at Data Cave in the past few weeks. In this blog, I’ll touch on AC, lights, and the parking lot.
Yesterday, two cooling towers were craned into place.
The past two weeks have been busy here at Data Cave.
Earlier this afternoon, a few technicians were onsite to power up the generator. Although this isn’t the first time the generator has been powered on (it was tested at the factory), it is the first time it’s been fired up onsite, with all the batteries and other bells and whistles installed.


Installation of the fire suppression system continues.

Installation of the irrigation system was completed today and a trial run was performed. Here’s Dave working on the automation for the system.

Additional electrical conduit was installed.

With the completion of the unistrut installation, more bus duct was installed down the west customer hallway.

The downspouts were installed on the east side of the building.

The last of the concrete was poured on Wednesday.

This week, I’ll start on with updates on the inside of the building and then we’ll head outside.
Work is going on both outside and inside the data center.
Today, a roofing crew is installing the rubber membrane on the roof.
Lots of progress at the site this week.