Taking Delivery…More Equipment
December 19, 2008 by Annie · Leave a Comment
Last Friday in the midst of the generator and power installation, we also received two cooling towers.
The capacity of each cooling tower is 1650 gallons per minute. The cooling towers will be set into place when construction nears completion.

Wednesday, we took delivery of a 550 ton water cooled chiller. Our chiller is on the back of the truck.

Two massive forklifts were used to move the 20,000 pound chiller into our existing facility.


Since this is a water cooled chiller, it will reside inside. The chiller will be moved into the Data Cave once the upstairs floor has been completed.