Building Updates
June 19, 2009 by Annie Tennis · Leave a Comment
The past two weeks have been busy here at Data Cave.
The final application of asphalt was applied to the parking lot.

We moved the chiller into place.

The air conditioning units for the front offices have been installed.


The vendor continued with the installation of the fire suppression system.

Lighting in the west customer hallway was installed and powered on.

Finally, the bus duct has been installed down the entire west customer hallway.