Cosmetic Updates

December 7, 2009 by Annie · Leave a Comment 

Over the past couple of weeks, we’ve spruced up the first floor office area.

Read more

Cooling Towers, Process Water, and Other Updates

December 2, 2009 by Annie · Leave a Comment 

Most of our efforts over the past week have been focused on the cooling towers and the process water.

Read more

Generator Load Test – Video

November 6, 2009 by Annie · Leave a Comment 

Two weeks ago, we load tested the generator. Here is video of that load test.

October Updates

October 30, 2009 by Annie · Leave a Comment 

Here’s a roundup of some of the work that has been completed in October.
Read more

Generator Load Test

October 23, 2009 by Annie · Leave a Comment 

Earlier this afternoon, we fired up the generator to do a load test.

photo

Stay tuned for video of the test.

More on the UPSs

October 2, 2009 by Annie · Leave a Comment 

The UPS manufacturer was onsite this week to bring the additional UPS capacity online.

Read more

Fire Suppression

September 25, 2009 by Annie · Leave a Comment 

Fire suppression systems have been installed in a handful of data suites.

Read more

The Fence

September 18, 2009 by Annie · 1 Comment 

The fence around the perimeter of Data Cave is now complete.

Read more

Additional UPS Capacity

September 15, 2009 by Annie · Leave a Comment 

A few weeks ago, we ordered additional flywheels for our UPS systems.

Read more

Blogging Hiatus

September 15, 2009 by Annie · Leave a Comment 

I apologize for the lack of blog post this past month.  Although, I haven’t been blogging about the progress being made at Data Cave, our crew has been hard at work.  I plan to elaborate on most of these items in the next week or two but here are a few things we’ve been working on:

  • increasing the capacity of the UPS systems,
  • data center cooling (processed water, chillers,etc.),
  • completion of the fence around the perimeter,
  • installation of additional fire suppression systems for individual data suites,
  • additional network configuration,
  • testing of monitoring systems, and
  • installation and configuration of security systems.

Additionally, we’ve been finishing up the front office area and we’ve also moved into the new facility.