Concrete and Block Update

February 16, 2009 by · Leave a Comment 

More concrete was poured today.

About half of the interior area of the second floor was finished today.  This is the east side of the pour.  In the background, you can see the concrete poured on Friday (it’s covered in blankets).

img_8662

This is the west side.

img_8663

Late last week, the block crew completed the south exterior wall.

img_8641

Today, the block crew worked on the north wall.

img_8670

Speak Your Mind

Tell us what you're thinking...
and oh, if you want a pic to show with your comment, go get a gravatar!