Doors, Paint, HVAC, Drywall, and Windows
May 8, 2009 by admin · Leave a Comment
Lots of progress at the site this week.
The dock leveler was installed.

The second floor bay door was installed.

Now that the concrete for the roof is poured, we’ve begun painting again.

Brandon is cutting the concrete on the second floor. The newly created holes are openings for the HVAC duct work.

Here’s a pictures of created openings.

Dry walling has begun in the first floor office area.

Finally, the windows have been installed.