Inside and Out

May 29, 2009 by · Leave a Comment 

This week, I’ll start on with updates on the inside of the building and then we’ll head outside.

The drywall crew is almost finished with the drywall in the first floor office area.  Below is a picture of a few members of the crew mudding.


Fire suppression was installed installed in a couple of rooms this week.


Jeremy has been installing unistrut in the west maintenance hallway.  Unistrut is a metal framing system.  Bus duct and pipes will be installed on this unistrut.


The gutters were installed on the roof earlier this week.


The driveway on the south side of the building is being completed.


Earlier today, grass seed was planted.


We also worked on the base for the cooling towers.  The cooling towers will sit on the metal beams seen below.


Speak Your Mind

Tell us what you're thinking...
and oh, if you want a pic to show with your comment, go get a gravatar!