More Steel, Block, and Cold
January 20, 2009 by Annie Tennis · Leave a Comment
Even last week’s subzero temperatures didn’t slow the crews down too much.
The steel crew has completed the west hallway.

The east hallway is over 50% complete.

The shipping/receiving area is almost complete, as well. There is a small section in the middle of the area that needs steel pan placed and welded. The picture below was taken from the middle of the shipping/receiving area.

The block crew has laid 10 courses of brick underneath the tent. The tent make it a bit hard to get a great photo but the pictures below give an idea of the progress.


Finally, here’s a neat shot I took of the block crew yesterday.