Since my last post, we’ve been focused on three projects here at Data Cave.
Project 1
Now that we have internet connectivity at Data Cave, Caleb and David have been focused on setting up the internal network.
Project 2
Installation of the chilled water (or cooling system) for the data center portion of the building.
The picture below shows the processed water tank and two processed water pumps. This equipment will tie into the chillers and provide cooling for the data suites.

In the foreground of the picture below, Gabe, Jowan, and Nic, are working on a third processed water pump.

Below, Jeremy and Glenn are attaching water pipe to the chiller.

Project 3
Outside, we’ve been installing the fence around Data Cave.