October Updates
October 30, 2009 by admin · Leave a Comment
Here’s a roundup of some of the work that has been completed in October.
We’ve been hard at work getting the cooling/processed water system up and running. Below is a picture of the cooling towers and piping.

Below, Nic and Glenn, work on the electrical panel for the chiller.

Cable tray has been hung and permanent lighting has been installed in the data suites.

Power distribution units (PDUs) and air handlers were delivered in October.
Below, Jeff, Caleb, Glenn, and Jeremy discuss PDU placement.

Below, Nic is wiring up a PDU.

During the second half of this month, we have been working on installing additional cameras throughout the facility.
Patrick is installing a camera in the maintenance area of the building.