Work is going on both outside and inside the data center.
An irrigation system is being built.

Two wells have been drilled for the facilities cooling towers. Below is a picture of one of the two wells.

We’ve begun painting the data suites.

The drywall in the first floor office space is coming along nicely.


Installation of the air conditioning units for the front office area has begun.

Ron and Nic have been hard at work connecting the circuit breakers for the flywheel UPS (think battery backup without the battery) to the electrical switch gear.