The Last Block

April 3, 2009 by · Leave a Comment 

This afternoon, Caleb laid the last of 93,000 blocks (yes, he isn’t a very good block layer).

img_9707

Block and the Office Area

April 2, 2009 by · Leave a Comment 

Block work continues on the east and west interior customer hallway walls.

Read more

Concrete, Framing, Grout, Block, and a Roof

March 26, 2009 by · 1 Comment 

Even though I haven’t posted in over a week, there’s been quite a bit of activity at the site.

Read more

Setting Steel for the Roof

March 18, 2009 by · Leave a Comment 

Today, the steel crew began erecting steel in the office area and Shipping/Receiving.

Read more

Block, Paint, and Steel

March 17, 2009 by · Leave a Comment 

Progress continues out at the site.

Read more

Block, Paint, and Sprinklers

March 12, 2009 by · 1 Comment 

Progress on the second floor block is coming along nicely.

Read more

Updates

March 6, 2009 by · Leave a Comment 

It’s been a busy week here at Data Cave.  I thought I would wrap up the week with a progress report.

Read more

Block Update

February 23, 2009 by · Leave a Comment 

Late Friday afternoon, the block crew finished laying the block for the exterior of the building.

Read more

Second Floor Concrete

February 20, 2009 by · Leave a Comment 

The second floor concrete is complete!

Read more

Concrete and Block Update

February 16, 2009 by · Leave a Comment 

More concrete was poured today.

Read more