Taking Delivery…More Equipment

December 19, 2008 by · Leave a Comment 

Last Friday in the midst of the generator and power installation, we also received two cooling towers.

The capacity of each cooling tower is 1650 gallons per minute. The cooling towers will be set into place when construction nears completion.

pc187312

Wednesday, we took delivery of a 550 ton water cooled chiller. Our chiller is on the back of the truck.

pc177265

Two massive forklifts were used to move the 20,000 pound chiller into our existing facility.

pc177283

pc177297

Since this is a water cooled chiller, it will reside inside. The chiller will be moved into the Data Cave once the upstairs floor has been completed.

pc177307

Speak Your Mind

Tell us what you're thinking...
and oh, if you want a pic to show with your comment, go get a gravatar!