The Office Area and Steel
April 16, 2009 by Annie Tennis · Leave a Comment
In the first floor office area, work continues on the electrical wiring, network cabling, and the plumbing.
Last week, the front windows for the second floor office area were enlarged.

Here’s a view from inside the building. Additionally, the final coat of paint is being applied in the office area on the second floor.

The second floor bathrooms have also been framed.

In the foreground, a member of the steel crew is affixing the angle iron to the block wall. In the background, members of the block crew are putting the finishing touches on the walls.

Today, the steel crew has started welding the steel pan in place.