February 24, 2009 by admin · Leave a Comment
There’s a flurry of activity over at the site today.
Some members of the block crew are working inside the building. They’ve been touching up cracks, filling in holes, and cleaning up.

Up on the second floor, the block crew has staged block. They’ll start laying block later today. Also, some of the interior doors have been set.

Another crew is insulating the exterior walls.

Additionally, the excavating crew is onsite working on the main water line to the building.

The block in the front of the building has been grouted so a few members of the block crew are taking down the scaffolding.