March 6, 2009 by · Leave a Comment 

It’s been a busy week here at Data Cave.  I thought I would wrap up the week with a progress report.

The block crew has been working hard on the second floor block.  The front office/data suite wall is now complete.

img_9188

They crew has also been working on block on the remainder of the second floor.

img_9180

Work on the water line and sprinkler system was completed.  (Note:  the sprinkler system is only for the office area of the building).  Here’s a view of the water pit.

img_9133

Here’s the water pit with the newly installed cap.

img_9185

Work on the electrical service continued.  In the picture below, Jeremy is working with the 500 MCM wire inside the generator.

img_9166

The process of painting has begun, as well.  A coat of block fill (much like primer) was applied to the walls of Shipping/Receiving.  img_9192

About half of the overhead steel in the front office has been painted, too.

img_9196