Updates Abound
November 4, 2008 by Annie Tennis · Leave a Comment
There has been quite a bit of progress at the site over the past week.
First, the concrete pads for the transformers were poured.


The double door frames on the lower west quadrant of the building were hung.

The utility poles were placed.

The block crew got quite a bit of work done on the lower east quadrant.


The block crew also started on the south exterior wall (in preparation for a concrete pour).



And here’s just a neat shot of the site from mid-afternoon.