Steel, Stairs, and Office Updates

April 9, 2009 by · Leave a Comment 

There’s been quite a bit of activity over at the site this week.

The steel crew has been setting steel most of the week.  Here’s a picture of them craning two pieces of steel for the roof.


The steel crew has set most of the steel for the roof.  A few data suites and the remainder of the east hallway remain.


Today the concrete crew poured the concrete for both staircases.  This picture is a few of the crew members pouring the concrete.


And here, a crew member is finishing.


More network cables are being pulled in the front office.


Today, the plumbing crew was onsite.  Below is the plumbing for the restrooms.


Additionally, the framers have been finishing up the framing on the first floor.